June 2025 Lift Construction Roundup
New lifts are being installed in four states.
Sunday, June 29, 2025, NewEnglandSkiIndustry.com

Construction is at various stages for eight lift projects slated to be built in New England this year.
2025 Lift Construction


Wachusett
Wachusett
Wachusett

Wachusett has already removed the Polar Express Quad to make way for a new Doppelmayr high speed six pack. Many components have already been delivered for the project.

Bretton Woods
Bretton Woods
Bretton Woods
Bretton Woods
Bretton Woods
Bretton Woods

Similarly, the Bethlehem Express Quad has been removed at Bretton Woods and much of the new Leitner-Poma lift has been delivered. Multiple footings have been poured for the new detachable quad.

Pats Peak
Pats Peak
Pats Peak
Pats Peak
Pats Peak

Like Wachusett and Bretton Woods, Pats Peak has also removed the Hurricane Triple. Significant clearing and excavation is taking place in the base area so that the terminal of the new lift can be at an elevation similar to that of the Peak Triple. Many footings were poured last year. The fixed grip quad will have a new SkyTrac terminal with Garaventa-CTEC towers and chairs from the former Lake Compounce lift.

Waterville Valley
Waterville Valley
Waterville Valley
Waterville Valley
Waterville Valley

Waterville Valley has performed initial excavation for the top terminal of its new T-Bar. The MND lift will run parallel to the bubble six pack to the base of the Chute. The shorter World Cup T-Bar has been removed.

Killington

Elsewhere in New England, Titcomb has removed its #2 T-Bar and has three-phase electric distribution lines being installed for its replacement, while Killington has removed the Superstar Quad to make way for the new six pack. There is no visible construction underway thus far for the Gateway Gondola at Loon.



Related Stories on NewEnglandSkiIndustry.com
  • Bretton Woods to Replace Bethlehem Express Quad - March 15, 2025
  • Pats Peak to Install Quad Chairlift - February 23, 2025
  • Wachusett to Install High Speed Six Pack - September 2, 2024
  • Lift Construction Kicks Off as Future Projects Go Through Permitting - April 27, 2024
  • Pats Peak First Ski Area 100% Open This Year - January 7, 2024
  • Bob Dunn Passes Away - April 21, 2023
  • Ski Season Starts Tomorrow - November 19, 2020
  • Lift Construction In Progress Across Northern New England - July 20, 2019
  • Lift and Lodge Construction In Progress Across New England - June 3, 2019
  • Bretton Woods Gondola Construction Progressing - May 4, 2019


  • More Information
  • Wachusett Mountain Ski Area on NewEnglandSkiIndustry.com
  • Bretton Woods News on NewEnglandSkiIndustry.com
  • Pats Peak News on NewEnglandSkiIndustry.com
  • Wachusett Mountain Ski Area on NewEnglandSkiHistory.com
  • Bretton Woods on NewEnglandSkiHistory.com
  • Pats Peak on NewEnglandSkiHistory.com


  • comments powered by Disqus
    Copyright 2014- NewEnglandSkiIndustry.com, All Rights Reserved